RFQ1/RFP1 SHORTLIST/SELECTION:

RFQ Issued to Firms: 02/24/15
RFQ Due to MSD: 03/18/15
RFP Issued:   04/29/15
RFP Due to MSD: 05/21/15
Selection Process Completed: 06/19/15

Projects Included in RFQ1/RFP1:

1.  Coldwater Creek WWTF Final Clarifiers Replacement (12504)

  • Crawford Murphy & Tilly Inc.
  • Donohue & Associates, Inc.                    SELECTED
  • Tetra Tech, Inc.

2.  Comprehensive Ammonia and Nutrient Removal Master Plan (12070)

  • Black & Veatch Corporation                    SELECTED
  • Jacobs Engineering Group, Inc.

3.  Degiverville Combined Sewer Relocation (11136)

  • ABNA Engineering, Inc.
  • Farnsworth Group, Inc.                           SELECTED
  • Gonzalez Companies, LLC

4.  Caulks Creek Forcemain Rehabilitation (11789)

  • Engineering Design Source, Inc.
  • M3 Engineering Group, PC                     SELECTED
  • Thouvenot, Wade & Moerchen, Inc.

 

RFP2 SHORTLIST/SELECTION:

Interest Statement Issued to Firms: 02/24/15
Interest Statement Due to MSD: 03/18/15
RFP Issued: 05/22/15
RFP Due to MSD:  06/16/15
Selection Process Completed:  07/17/15

Projects Included in RFP2:

1.  Lemay Pump Stations 1 and 2 Improvements (12488)

  • Crawford Murphy & Tilly Inc.
  • Donohue & Associates, Inc.                   SELECTED
  • Wade Trim, PC

2.  Natural Bridge Rd - Darby to Chevrolet Combined Sewer Relief (12536)

  • Access Engineering, LLC                       SELECTED
  • Cole & Associates, Inc.
  • Heideman & Associates, Inc.

3.  Deer Creek OMCI Stormwater Design (Contract A) (12461)

  • CDG Engineers, Inc.                              SELECTED
  • CMV - Cochran, LLC
  • EFK Moen, LLC

4.  Rosewood Lane & Woodard Dr. Storm Sewer (10347)

5.  Big Bend to Papin Storm Sewer Phase I (10035)

  • EDM Incorporated
  • Hart Engineering, LLC                           SELECTED (10035)
  • Oates Associates, Inc.                           SELECTED (10347)
  • RJN Group, Inc.
  • TREKK Design Group, LLC

6.  Hudson Rd. #1401 - #1405 Bank Stabilization (MCDW-120) (10020)

7.  Cottage #206 Storm Improvements (10302)

  • HR Green, Inc.                                       SELECTED (10020)
  • Reitz & Jens Inc.
  • Stantec Consulting Services Inc.           SELECTED (10302)
  • Stock & Associates Consulting Engineers, Inc.
  • Williams Creek Consulting Inc.

 

RFP3 SHORTLIST/SELECTION:

Interest Statement Issued to Firms: 02/24/15
Interest Statement Due to MSD: 03/18/15
RFP Issued: 06/19/15
RFP Due to MSD: 07/14/15
Selection Process Completed: 08/14/15

Projects Included in RFP3:

1.  General Services Agreement - Construction Management (2016) (11752)

  • AFRAM Corporation                                    SELECTED
  • Basilico Engineering Incorporated
  • Shalom Services Corporpation

2.  General Services Agreement - Facility & Sewer Design (2016) (11760)

  • George Butler Associates, Inc.
  • Horner & Shifrin Inc.
  • Tetra Tech, Inc.                                           SELECTED

3.  General Services Agreement - Survey Services (2016) Contract A (11764)

4.  General Services Agreement - Survey Services (2016) Contract B (12394)

5.  General Services Agreement - Survey Services (2016) Contract C (12395)

6.  General Services Agreement - Survey Services (2016) Contract D (12405)

7.  General Services Agreement - Survey Services (2016) Contract E (12406)

  • Civil Design, Inc.                                         SELECTED (12405)
  • Clayton Engineering Company
  • Gateway Land Services, Inc.
  • Hanson Professional Services inc.             SELECTED (12406)
  • Juneau Associates Inc., PC
  • Kuhlmann Design Group, Inc.
  • Sabur, Inc.                                                   SELECTED (11764)
  • Sterling Company                                        SELECTED (12395)
  • Volz Incorporated                                         SELECTED (12394)